Skip to Content
0
Former Member
Jul 12, 2008 at 03:04 AM

Roll-up of POC in the project hierarchy?

55 Views

hi all,

is it possible to let the POC roll-up from activity to the higher level elements in the hierarchy structure?

i am getting results for POC if the activity but it does not roll-up. i wondering if this is possible (just like the POC weight, the figures add up to higher levels). it it is possible, how do i do it? (i wish to use either quantity proportion or degree of processing as the measurement method)