Hi,
I have created standard project definition with work breakdown structure(WBS) in T-code CJ91.Is Standard project definition transportable from one client to the other?
Thanks,
Anitha
I dont think so.
Standard WBS are saved PRPSS table which of type 'A' which means transaction data table. It cannot be transported.
Regards,
Ramesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi anitha,
Project definition and WBS elements are the Master data for PS. Master data can be copied from one client(Development) to another client (Quality) by doing copy client.
Take the help of your basis team for master data copying.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi anitha,
As I known we can copy standard project defintion with WBSE by making copy client. for that standard PRJ definition should be in release status.
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
103 | |
12 | |
11 | |
6 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.