on 07-11-2008 3:16 AM
Hello Time Schema Guru,
How to compare the evaluated day of time evaluation to a fixed date (Date shouldn't be maintained in IT 0041)?
So that I can code, If the fixed date is less than time evaluated day do "xyz operation" else do "abc operation".
I looked into the help of VAR, HRS=Y and HRS=B operations and couldn't figure out the answer.
Appreciate prompt support in this regard and points will be rewarded.
Best Regards,
Sunny
Have you tried HRS= YAA.. i guess that should solve your requirement. But you need to store that fixed day as a hiring day or some other day in IT 41