Order based vs time series IBP

Feb 22 at 10:38 AM

82

avatar image

Hi all

Using a planning area copied of SAP74 I have some doubts.

The requirements is planning order based (operative planning, forecast consumpiton and son on..) but running with no restrictions (like tiem series heuristic)

Does constrains forecast run creates new proposals as stock transfer requisitions?

If I used also time series heuristic, the same key figure can be used for both?

If I want to run and order based heuristic, what should I use? constrain forecast with no constrains or time series heuristics.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Rohit Ranjan
Feb 26 at 11:51 AM
0

Hi Carlos,

You can run constraint forecast run to generate new STRs.

There are some common key figure used for time series and order based planning. See the link below-

Common key figures

Thanks,

Rohit