Dear Experts,

In capacity leveling screen CM21 I can see my order's operation and phases adhering to the relationships in the un-dispatched, lower section. But when I dispatch my complete order they do not adhere to the relationships maintained in master recipe. I have also marked 'consider operation sequence in the order' in strategy profile, but it still doesn't work.
What should I do? is there a strategy setting in CM21 which I'm missing? Should I do something with master recipe?

Regards

Shankar

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Feb 22 at 06:06 PM
0

Hello

You should not use CM21 for dispatching process orders, since there is a specific profile for process orders.

Check my answer in the following thread:

https://archive.sap.com/discussions/thread/3599516

Regards,

Caetano