Hi gurus,
Consider the following scenario:
Material A. It has 3 operations. Operation no. 2 is to be processed at 2 different work centers, so that the load is distributed and total operation time is reduced.
Production order is of 100 pcs. For operation 2, 50 pcs. are processed on 1 work center and remainig 50 pcs. on another work center. Both happen simultaneously.
How can i manage this in the routing with different %?
I will reward points all answers!!!