Process Order Archiving

Former Member
0 Kudos

Hi All,

Can any one explain what steps needs to be taken for archiving PR_ORDER.

I am looking for below scenario:

1) Setting up of Residence time for process order and how it works?

2) If any additional steps needs to be taken care to archive Process Orders, apart from the process which is followed to archive data from SAP.

--Thanks

Pankaj.K.S

3 REPLIES 3

Former Member
0 Kudos

HI Pankaj,

I dont know much more about this archiving.

Just a simple idea.

First of all go to T-code SARA , entert the object name(PR_ORDER) and select the database table , from here u can get all the table used in this object. I think there are 181 tables are used.Note down the tables.

Now go to T-code --DB02 and select detailed analysis tab give ur table name , from here u can find out total memory space taken by table in sap.

NOw go to T-code TAANA , go for back ground job schedule for each table and find out the total entries in the table.

REward if helpful........

Thanks,

0 Kudos

Hi Baidyanath,

Thanks for your help. I have done all this excercises before, but thing here is the preprocessor job is setting the deletion flag and deletion indicator and the write job is not archiving that data.

Please let me know if you have any information.

--Thanks

Pankaj.K.S

0 Kudos

Check if you have maintained the scheduling type of the process orders (application specific customizing or TA CORN).

best regards

Martin