Hi All,
When i'm analysing CO03>Goto>Cost-->Analysis.i'm getting different result for production order costs?
last week,i can see overhead cost in target cost column(Target cost = standard cost) and now i cant see for newly created production orders.
At what point the target cost will be calculate in Production order?any help is appreciated.
Thanks,
Rau