Dear All,
It is related to order bom.
I have created a material bom with BOM usage 3 - Universal.
then I have created routing for the same material with usage 3 universal.now i have created sales order for the same material.then i have created an order bom using cs61 and added one more component to it.
with referance to sales order i had changed the routing of the same material and assigned the new component in the roution operation.Now when i tried to take MRP for the same material using md02 and md50 both time the order bom is not exploded and only the finished product level is planned.the depended materials are not planned
Please help me to solve the problem.
thank you
Regards
Prashant