MIGO -> Goods Issue -> Other -> 551 while stock is confirmed

Former Member
0 Kudos

Dear experts,

I searched community and could not find an answer to this scenario;

Stock Situation

Material : ABC

Plant: XYZ

Stock on hand: 100 units

Requirements Situation

Sales order no: 123

Line: 10

Material: ABC

Plant: XYZ

Order Quantity: 100

Confirmed QTY:100

---------------------------------

Scenario

System allows a user to perform MIGO -> Goods Issue -> Other -> 551

on material ABC at plant XYZ with quantity 100 even though 100 units are confirmed in Sales Order or if 100 units are in a delivery waiting to be PGI.

I'd like to know if this is standard behavior as I think the system should not allow a material to be scrapped/issued if it is confirmed by ATP in sales order or the quantity is against an open outbound delivery.

Thanks

Accepted Solutions (1)

Accepted Solutions (1)

JL23
Active Contributor
0 Kudos

how had you searched? Try it with this term, I get 195 results: "dynamic availability check" site:sap.com

MIGO does not check by itself, you have to tell MIGO that it shall check to avoid that it takes stock which is allocated to an order.

Looking at your movement type it does not really make much sense to do an availability check when you scrap material. You scrap material when the quality is bad or a drum with chemicals spilled. You do such checks if you post before you physically issue it to avoid that you give reserved material to a cost center, the other way around does also not make much sense as it is often too late to get it back.

Former Member
0 Kudos

Jürgen L,

To be frank, I was not aware that my issue related to "dynamic availability check". Now that I know I can see what needs to be done.

Many thanks

Answers (0)