Hello all,
I'm dealing with the following situation:
finished product - strategy group 81
semifinished product - strategy group 70
PIRs on semifinished product:
100 pieces month 1
100 pieces month 2
100 pieces month 3
consumption mode for semifinished product: 200 days bckw, 200 days frw
Sales order for finished product of 300 pieces in month 1.
Expected result:
system checks for semifinished product availability in Sales Order, proposes confirmation for 300 pieces, scheduled based on semifinished availability (100 + 100 + 100)
Actual result:
system checks for semifinished product availability in Sales Order, proposes confirmation for 300 pieces, 100 pieces first, and then for 200 pieces at month 3 date.
Is there any explanation for that?
Regards
Nue