Hello Colleagues,

I found that IS-Mill functionality is by default activated in S4 HANA which is creating below problem in my project:

1. Variant configuration is not being transferred to Production order created in the system (because of which BOMs and Routings configured are not determined automatically)

2. This is also happening while converting Planned order to Production order


How can I overcome this issue to be able to utilize variant configuration through out the process..


Thanks,

Mohammad

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Caetano Almeida
Feb 25 at 04:06 AM
1

Hello

In SAP S/4HANA it's mandatory to create a production version, so that the BOM and the routing can be exploded.

Check this blog for details:

https://blogs.sap.com/2017/05/22/s4-hana-new-report-to-create-production-versions-with-routing-during-the-migration/