Hello Gurus,

we are facing with following issue in our environment. We have Z transaction for sales order, where Production Department confirms production date. This date is then visible in Sales Order. The point is - MRP run schedules purchase requisitions by delivery date, not production date which is mentioned in sales order.

My question is - is it possible to customize MRP Run to not schedule purchase requisition by delivery date but production date which is set in sales order?

Accepted Solutions (1)

Accepted Solutions (1)

Caetano
Product and Topic Expert
Product and Topic Expert

Hello

You can use BAdI MD_CHANGE_MRP_DATA to change the sales order requirement date for MRP. If you activated the performance optimizations for MRP on HANA, then the best BAdI to use is MD_ADD_ELEMENTS.

Regards,

Caetano

0 Kudos

Hello Caetano,

thank you for you answer.

Caetano
Product and Topic Expert
Product and Topic Expert
0 Kudos

Hi Paul,

If the question is answered, can you please close it by accepting the correct answer?

Regards,

Caetano