We are using repetative manufacturing, I want to know if I can group all materials by set-up time - hence reduce change overtimes from one group of products to the other.
Can I use Setup group category & setup group Key with planned orders.
Thanks in advance.
1.Set up grop key and categroy will not help in the REM manufacturing table.
2.This setup group and matrix will help in the capacity planning only.Where dispatching can be done by grouping at the setpu group key etc.
3.Even that would complicate the things becuase again we need to check what things system has pushed.
4. But int he capcity planning table -graphical it can belp you to highlight the order by the setup grou key .
5.So if you are looking for a funcitoanlity of grouping the materials in the setup group then that is not possible.
let us know if you have anydoubts..
reg
Dsk
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
97 | |
11 | |
11 | |
6 | |
6 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.