on 07-07-2008 11:44 AM
Hi All,
I have created a sub-con PO and after that some changes are required in the BOM and the same are done. How to re-explode the BOM in the same PO and what will be the impact of the same on MRP?
Thanks in advance
Radha Krishna Madineedi
Hi,
Go to Purchase order display ME23N and in PO Item detail tab Material Data tab click on BOM explode. Then it will explode new BOM.
Reg,
Ashok
Rewards welcome.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
I created a PO > BOM was exploded > after I changed the BOM (validity 'from' in the past) > the BOM in PO remaines the same and I cannot change it.
So, you have to do it manually I' afraid...(on 'material' tab of your PO item)...because we are speaking about an already issued PO...
Just my opinion I'm not sure...
BR
Csaba
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Its is possible to rexplode BOM
thanks
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.