Hi All,

I have created a sub-con PO and after that some changes are required in the BOM and the same are done. How to re-explode the BOM in the same PO and what will be the impact of the same on MRP?

Thanks in advance

Radha Krishna Madineedi

Accepted Solutions (0)

Answers (3)

Answers (3)

former_member192897
Active Contributor
0 Kudos

Hi,

Go to Purchase order display ME23N and in PO Item detail tab Material Data tab click on BOM explode. Then it will explode new BOM.

Reg,

Ashok

  • Rewards welcome.

csaba_szommer
Active Contributor
0 Kudos

Sorry, my information was incorrect. Ashok is right.

csaba_szommer
Active Contributor
0 Kudos

Hi,

I created a PO > BOM was exploded > after I changed the BOM (validity 'from' in the past) > the BOM in PO remaines the same and I cannot change it.

So, you have to do it manually I' afraid...(on 'material' tab of your PO item)...because we are speaking about an already issued PO...

Just my opinion I'm not sure...

BR

Csaba

Former Member
0 Kudos

Its is possible to rexplode BOM