Maintenance Order Operation task wise the Actual work is not calculating

In every Month After scheduled of Maintenance order inside Operations tasks the actual work cell is not in white color to edit & its not calculate any no.s

I don't know why ?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Feb 20 at 08:17 AM

    The Actual Work field (AFVGD-ISMNW) on the operation should never be open for data entry.

    The field is summated from the confirmation data (IW41).

    Check to see if you are using BADI IWO1_SCREEN_MODIFY. If so, deactivate it to see if the standard functonality returns.

    PeteA

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 20 at 10:50 AM

    Hi,

    Additional to Pete responce, Actual work will be updated based on your confirmation.

    If possible share the screenshot of the information you are looking for.

    Regards

    Terence