Scheduling XS job on last day of each month

Feb 19 at 09:18 PM

62

avatar image
Former Member

Hi,

How can we schedule an XS Job to run on last day of each month? So I cannot hard code the xscron values.

Any help with the xscron syntax would be much appreciated!

Thanks in advance!

Upamanyu Mukherjee

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
Lars Breddemann
Feb 19 at 09:37 PM
0

Why don't you schedule the job on the 28th, 29th, 30th and 31st of every month and perform the check for the last day of the month in your job. If it isn't you simply exit if it is you execute the job.

Show 1 Share
10 |10000 characters needed characters left characters exceeded
Former Member

Sorry to reply to late! Yes this is the other idea I had and eventually this is what I did like you suggested.

Thanks!!!