sales order bom is not transferred to production order

Dear SAP expert,

I face below scenario: the finished goods are similar, different customer has different small requirement, we would like to use one finished-goods material number with sales order stock. the process is below:

1, Sales team create Quotation (VA21), then create sales order BOM (CS61)

2, Calculate product cost and assign sales order price, then issue quotation.

3, When customer accept, create sales order which is copied from quotation.

4, Costing before release to production order.

5, Create production order against to sales order.

Currently, I test it in IDES system, it is complex process. I have some issue as below:

1, quotation BOM can't be transferred to sales order BOM, no new sales order BOM is created, we have to create again with copy.

2, When I create production order, sales order BOM can't be transferred to production order as below: it looks BOM is found, but component can't be copied into production order.

I am confusing this process, anybody can help me? Thank you.

pp2.jpg (75.1 kB)
pp3.jpg (26.4 kB)
pp4.jpg (82.7 kB)
pp1.jpg (76.8 kB)
Add comment
10|10000 characters needed characters exceeded

  • Former Member

    the assignment of production order is to the sales order.

    Now I fix the problem that BOM is copied from sales order to production order

    Current open issue is that BOM is not copied from quotation to sales order
  • Please post this as a separate question. And if the original question has been answered then kindly close it (see this blog).

  • Hello

    In your production order, the assignment is to the sales order or to the quotation special stock?

    Regards,
    Caetano

  • Get RSS Feed

3 Answers

  • Feb 19 at 11:39 PM

    you need to create a material BOM (usage '1')

    use the CS01

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 20 at 03:24 AM

    Hi,

    When you create the Sales Order BOM, you need to use usage 1 as shown below then this BOM will be copied to Planned order ( when you run MRP) and then when you convert this planned order to production order those components in the BOM will get copied to production order and of course this will work in make to order scenario like planning strategy 20.

    Thanks

    Kumar

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 28 at 09:39 AM

    Hi,

    Please create a sales order BOM with usage 1 or 3. It will help you to transfer the Sales BOM into your production order.

    Hope it helps.

    Best Regards

    SenthilNathan Karunanithi