PM Order Backflush from Q Stock Fails

I have created a Maintenance Order and Specified components with Special Stock indicator Q and Backflush. But when I do IW41 confirmation, the backflush fails. Could you please let me know if I'm missing any configuration.

Add comment
10|10000 characters needed characters exceeded

  • Yes, I went to COGI and see message "Deficit of quantity". But I do have stock available.

    But if I change the special indicator from 2 (project stock) to Blank, then backflush works fine.

  • Hello

    Do you have stock under the project special stock? It seems that you are trying to consume from special stock Q but there is not enough quantity under the project special stock.

    Regards,

    Caetano

  • Seems , you have not maintained your stock as "Q- Project Stock".

  • Get RSS Feed

1 Answer

  • Feb 16 at 08:18 PM

    Have you setup your stock determination?