We have a requirement in program to read reference capacity data in Tcode CR13 for date calculation. The program should calculate dates based on the work days defined in reference capacity. Work days in CR13 are based on Valid from/Valid to date and capacity data. The plant is using 5 day (Mon-Fri) calendar and blocking some Fridays in reference capacity.

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Caetano Almeida
Feb 16 at 06:50 PM
0

Hello

Try with CR_CAPACITY_AVAILABLE_PERIODS.


Regards,

Caetano

Share
10 |10000 characters needed characters left characters exceeded
avatar image
Former Member Feb 20 at 05:02 PM
0

Caetano,

Thank you for the info. I will test this function module. Do you know whether it is considering work center and reference capacity or only work center?