Is there a function module to read reference capacity data accessed thru Tcode CR13?

We have a requirement in program to read reference capacity data in Tcode CR13 for date calculation. The program should calculate dates based on the work days defined in reference capacity. Work days in CR13 are based on Valid from/Valid to date and capacity data. The plant is using 5 day (Mon-Fri) calendar and blocking some Fridays in reference capacity.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Feb 16 at 06:50 PM

    Hello

    Try with CR_CAPACITY_AVAILABLE_PERIODS.


    Regards,

    Caetano

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 20 at 05:02 PM

    Caetano,

    Thank you for the info. I will test this function module. Do you know whether it is considering work center and reference capacity or only work center?

    Thiagu