mrp run

Hi fr pl anyone give me solution

Material A can be manufactured using material B and material B can be manufactured with material C. Material B has a procurement type both. Whenever we procure the material from the vendor at that time the planning for the material C should not happen in the MRP run. Similarly when material B is produced in-house at that time material C should be automatically planned in the MRP run. More over at the time of MRP run the system should ask automatically whether the material B is procured externally or internally.

Add a comment
10|10000 characters needed characters exceeded

Related questions

2 Answers

  • author's profile photo Former Member
    Former Member
    Posted on Jul 04, 2008 at 08:03 AM

    Hi,

    In material master select Procurement type X.

    After MRP run planned order will be create for material B.

    If you want to produce in inhouse, convert this planned order into prod order. So system will consume material C.

    If you want to procure from external, convert this planned order into Pur req.

    From MD04 screen, you can convert the planned order into prod order or P.R

    Regards,

    Dharma

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member Former Member

      Hi Jeya,

      I feel Instead of running MRP you should go for MPS , so that you can plan the material on A level and the B level.and so no planning needed for C level materials

      In your case A is FERT, B is Halb and C is Roh i feel from what you said.

      So when you run MPS for FERT that is level A the BOM for A will be exploded and the plannin for the next immediate level that is B Halb will also be done and so you will not have to plan the material for C after making the Purchase requisitons for B.

      Hope this one helps

      Regs

      Dardo

  • author's profile photo Former Member
    Former Member
    Posted on Jul 04, 2008 at 04:59 PM

    Hi jeya,

    You can control the planning of material as mentioned by Dharma

    But i dont think its possible to control(stop) the planning of material C as it is a dependent requirement so it will be triggered automatically as & when there is a requirement for the parent material

    Only option how you can stop is putting MRP type as ND but that will not solve your purpose/requirement

    Hope the above is clear

    Regards,

    SVP

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.