Hi All,
I have a scenario where PS & IM interlinked.
I have created a Inv.Program & Position ID's under it.I have assigned two 1st level WBS Elements to one of the Position ID.
As per my client requirement,One position ID is assigned to 2 projects.
& I have done cost planning (CJ40) for the projects.
my requirement is, I need a report based on Position ID.
I would like to see a report ,which gives position ID wise Projects & then those projects Cost Planning Values.
Is that CJ40 values linked to IM Position Id's?
Kindly suggest me a Std SAP Report ,if available or else guide me how to achieve this.
Thanks in Advance !!
Suresh Kumar
nil
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
One easy option:
In any plan costs reports under PS, choose the DB profile usually 000000000005 Standard selection (cap. invest.program) instead.
Mention the IM Program/ID/Year, you should be viewing the plan costs at positions level.
Regards
Sreenivas
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
S_ALR_87012809 will help you.
Hope you have rolled up the planned cost to IM program by IM34.
Regards
Edited by: Shrikant Rakate on Jul 1, 2008 7:45 PM
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
88 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
2 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.