IM-PS Planning cost detailed Report

Former Member
0 Kudos

Hi All,

I have a scenario where PS & IM interlinked.

I have created a Inv.Program & Position ID's under it.I have assigned two 1st level WBS Elements to one of the Position ID.

As per my client requirement,One position ID is assigned to 2 projects.

& I have done cost planning (CJ40) for the projects.

my requirement is, I need a report based on Position ID.

I would like to see a report ,which gives position ID wise Projects & then those projects Cost Planning Values.

Is that CJ40 values linked to IM Position Id's?

Kindly suggest me a Std SAP Report ,if available or else guide me how to achieve this.

Thanks in Advance !!

Suresh Kumar

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

nil

Former Member
0 Kudos

One easy option:

In any plan costs reports under PS, choose the DB profile usually 000000000005 Standard selection (cap. invest.program) instead.

Mention the IM Program/ID/Year, you should be viewing the plan costs at positions level.

Regards

Sreenivas

Former Member
0 Kudos

Hi sreenivas,

Thank you very much for the details.

Former Member
0 Kudos

S_ALR_87012809 will help you.

Hope you have rolled up the planned cost to IM program by IM34.

Regards

Edited by: Shrikant Rakate on Jul 1, 2008 7:45 PM

Former Member
0 Kudos

Hi shrikant,

Thank you very much.It is working fine.Thanks a Lot.