MRP - Planned order Rescheduling not happening

Dear Experts,

I have gone through many threads regarding this problem on SCN and have done relevant setting in OPPQ, OPU5, OPUZ(PP-PI) and Material master but all in vain. I'm attaching screen shots of all these screens with addition of MRP results in MD04.

Problem is MRP is not rescheduling planned orders with regards to capacity in master recipe or in house production time in material master. It's pilling all the orders on a single day where as each order takes about 2 days production time. Kindly help as this is S/4HANA and I'm lost.

1) OPU5

2) OPUZ

3) OPPQ

4) MD04

5) Material Master (MM03)

Regards,
Shankar

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Feb 16 at 03:35 PM

    Hello Shankar

    Rescheduling planned orders based on capacity was never an MRP capability and it is still not a capability in S/4HANA.

    However, as of S/4HANA release 1610, you have Embedded PP/DS, which allows you to run a product heuristic that plans materials and capacity at the same time, and which would resolve this issue.

    Regards,

    Caetano