How to copy previous forecast to new month in Demand Plan?

Feb 16 at 08:36 AM

75

avatar image

Hello,

I would like to ask your help on how to copy previous month forecast quantity to next new month in Demand Plan.

Regards,

Toom

10 |10000 characters needed characters left characters exceeded

Hi Toom,

Why would you want to copy the forecast of previous month to the next month in a demand plan ? The system will calculate forecast for each month provided its in the forecast horizon. If the "next month" is not in the forecast horizon you can always roll the demand plan isnt it ?

Are you looking for an option to move the unconsumed forecast to the next month ?

Regards,

Anand

0
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Best Answer
avatar image
Former Member
Feb 22 at 09:38 AM
0

Hi Toom,

You can achieve this easily through macros in DP. Check online help documentation for the macros.

Please share the screenshots if you are facing some difficulty.

Thanks & Regards,

Sonali

Show 2 Share
10 |10000 characters needed characters left characters exceeded

Dear Sonali,

I have successfully upload it through Excel file. But please advise how I can download key figure of specific demand plan. Currently, when click on download, it has to download all key figure from all demand plan which take time to finish downloading.

Thanks and regards,

Toom

0
Former Member

Dear Toom,

From the key figure selection option, you can select that particular keyfigure for which you want to download the data.

Kindly check.

Thanks,

Sonali

0