We recently changed our PR workflow from item based approval to Header level approval. Approvers are determined by 1st line item's cost center. Everything is working fine BUT when requisitioner modifies cost center a new work flow is not triggered with new approvers by removing task from previous pending approver's inbox.

Note: Issue is only with workflow & work items.
PR in MExxN transaction screens shows modified approvers and new approvers can approve using MExxN transaction issue is only with WORKFLOW which is not triggering new workflow and not creating new work item in new approvers inbox and not removing work item from previous pending work item from old approver.

Are we missing anything?

Thanks,

Pradeep

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Feb 15 at 11:21 PM

    This OSS note has a list of settings to be checked

    597784 - Workflows WS00000038, WS20000075 and WS20000077

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 16 at 02:06 AM

    Hi Pradeep

    I assume you mean PR release strategy not being triggered right?

    Found an OSS note which answers this question 493900

    I believe question 3 and 4 in this note might be what you are looking for

    Check the release indicator no:4 has condition maintained as values >=0 ,

    then only the value change will apply for re release trigger.


    Regards

    Vinita