We recently changed our PR workflow from item based approval to Header level approval. Approvers are determined by 1st line item's cost center. Everything is working fine BUT when requisitioner modifies cost center a new work flow is not triggered with new approvers by removing task from previous pending approver's inbox.

Note: Issue is only with workflow & work items.
PR in MExxN transaction screens shows modified approvers and new approvers can approve using MExxN transaction issue is only with WORKFLOW which is not triggering new workflow and not creating new work item in new approvers inbox and not removing work item from previous pending work item from old approver.

Are we missing anything?

Thanks,

Pradeep

10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

2 Answers

Jürgen L
Feb 15 at 11:21 PM
1

This OSS note has a list of settings to be checked

597784 - Workflows WS00000038, WS20000075 and WS20000077

Show 1 Share
10 |10000 characters needed characters left characters exceeded

Thank you Jurgen, I will check it.

0
Vinita Kasliwal Feb 16 at 02:06 AM
0

Hi Pradeep

I assume you mean PR release strategy not being triggered right?

Found an OSS note which answers this question 493900

I believe question 3 and 4 in this note might be what you are looking for

Check the release indicator no:4 has condition maintained as values >=0 ,

then only the value change will apply for re release trigger.


Regards

Vinita