DC520 Validation (at complete) is not happning for the 2nd occurance of the SFC

SFC is started at the operation (OP1) mandatory DC is performed and SFC is completed. Very next operation(OP2) SFC is started and NC was logged for the disposition, after the disposition route is executed SFC is back to the OP1 , at OP1 SFC is started and DC is not asked (DC520 is hooked at Pre complete at OP1) and I could able to complete the SFC at OP1. I was expecting that system will ask the DC at OP1.

I had seen this issue in the v15.1.3.18 but this was normal when we were using v15.1.3.8.

please suggest?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

2 Answers

  • Best Answer
    Mar 10 at 02:06 PM

    Hello

    The bug is to be fixed in ME 15.1.3 Patch 21.

    Best regards,

    Alex.

    Add comment
    10|10000 characters needed characters exceeded

  • Mar 15 at 04:57 PM

    Thanks I got the similer feedback from SAP on the ticket logged