on 02-14-2018 6:16 PM
SFC is started at the operation (OP1) mandatory DC is performed and SFC is completed. Very next operation(OP2) SFC is started and NC was logged for the disposition, after the disposition route is executed SFC is back to the OP1 , at OP1 SFC is started and DC is not asked (DC520 is hooked at Pre complete at OP1) and I could able to complete the SFC at OP1. I was expecting that system will ask the DC at OP1.
I had seen this issue in the v15.1.3.18 but this was normal when we were using v15.1.3.8.
please suggest?
Hello
The bug is to be fixed in ME 15.1.3 Patch 21.
Best regards,
Alex.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Thanks I got the similer feedback from SAP on the ticket logged
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.