What Posting Happened during TECO / CO15

Dear Sir,

We request you to kindly guide as what posting / status changes takes place during the execution of following transactions :

a) In transaction CO11n , when giving Confirmation Type --> "Final confirmation"

b) In Transaction CO15

c) TECO of production Order

We will be highly greatful for the help pl .

Rgds

B Mittal

Add a comment
10|10000 characters needed characters exceeded

Related questions

3 Answers

  • Posted on Jun 30, 2008 at 08:01 AM

    Hi,

    In both CO11n & CO15, if you do the Final confirmation then The status will be CNF.

    If you do the Auto GR during Confirmation then the Status DLV.

    TECO is the System status, when you do the Technically Complete.

    I hope I have understood your query correctly, if not revert for further discussion..

    Regards,

    Siva

    Add a comment
    10|10000 characters needed characters exceeded

  • author's profile photo Former Member
    Former Member
    Posted on Jun 30, 2008 at 08:33 AM

    co11n is operational confirmation and co15 is production order confirmation. both can be partially confirmed or fully confirmed. for partial it is PCNF anf for final it is CNF.

    after the goods reciept with tr.code mb31 and movement type 101 for the whole order quantity the status will be DLV that is fully delivered.

    it is then you have to do TECO for order settlement.

    hope u r clear if not get back.

    sanjeev

    Add a comment
    10|10000 characters needed characters exceeded

    • Former Member

      Hi,

      Once you do TECO for an order, you will not be able to make any other confirmations or changes on the order. Also, all the reservations of the order will be deleted and the order will no longer considered for MRP run and even it wont appear on the MD04 screen.

      Pl revert if you any other query.

      Aravind

  • author's profile photo Former Member
    Former Member
    Posted on Jul 04, 2008 at 01:04 AM

    Hello BV

    Functionally when we complete the manufacturing activities of the Product we need to confirm what is produced and what is consumed for a prod order that is nothing but Confirmation CO11n or CO15 where ofcourse if you have compleetd the order then can be finally confirmed and if partial completed the partial confirmation CNF and PCNF statuses at this level. This will also result in the goods receipt of finished product and issue of the components from the stock.

    TECO is Technically complete- this is the step where we say that the Prodcution activity is completed and upon this status we cannot change the order however you can revoke Teco status if you need to..

    Please let me know if this makes sense.

    Thanks

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.