Hello

In order for the availability check to be carried out, what steps must be defined in the system.

Thanks

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    Jun 28, 2008 at 09:55 PM

    In order for the availability check to be carried out the following data must be defined in the system

    • The availability check must be switched on at the requirements class level in transaction OVZG

    • For the availability check in the sales document, the indicator must be set at the schedule line category level in transaction OVZ8

    • A requirements type must exist by which the requirements class can be found in transaction OVZH

    • A plant must be defined in the sales order for the line item. It can either be automatically proposed by the system from the customer, the customer material information record, or the material master record. It can also be entered manually in the document.

    • A checking group must be defined in the material master record in the MRP 3 screen in the Availability check field.

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 29, 2008 at 05:38 AM

    Dear Manik Rao

    - In Material Master MRP3 view, Availability Check should be maintained

    - For schedule line category, field "Availability" should be checked in VOV6

    - In OVZG, Availability Check should be switched on

    thanks