Skip to Content
avatar image
Former Member

Checking rule - availability check

Hello Friends,

When availability check is done at sales order, in display scope of check, system determines checking rule as A.

From where does the system determine this checking rule.

Thank you

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

2 Answers

  • Best Answer
    Jun 28, 2008 at 10:56 PM

    The checking rule is used to control the scope of the availability check for each transaction in sales and distribution.

    The control of the availability check is defined by the checking group on the material master record and the checking rule representing the transaction.

    The checking rule may be configured in the system depending on the application or module, but in the sales and distribution module, it is predefined.

    In other words, when you create a sales order, system determines checking rule as A.

    If it is make to order stock, system determines checking rule as AE.

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 29, 2008 at 05:33 AM

    Dear Manik

    It is predefined in SAP such that

    - for sale order in make to stock scenario, it is A,

    - for sale order in make to order scenario, it is AE

    - for Delivery, B

    thanks

    G. Lakshmipathi

    Add comment
    10|10000 characters needed characters exceeded