on 06-28-2008 5:22 PM
Hi Gurus.
In this scenario I want to convert the PIR's that I am getting from APO in inactive version and I want to convert it into active version before running the MRP.Pls suggest how to do it?
Hello Dardo,
Mostly you can do planning with different version numbers in planned independent requirent.Unless and until you active the version, it will not transfer the independent reqmt to stock requirement list.
To active any version number, go to change mode (T.C MD62) and give the material number, plant and version number which you want to activate and press enter, it will go to next screen.There besides material name field there is check box for version.Just tick that.Now if you see in stock reqmt list (T.C MD04) you will see the indep reqmt got transfered.
Hope this way you will resolve your problem.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
You can try Transaction MS64.In this,you can copy PIRs which has come from APO in say version(X) say,which is an active version into another version (Y) and select inactive.
Plzreward points if found useful.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
89 | |
8 | |
7 | |
4 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.