1.How can we get 10 shipto party at a time in customer master?

what is the procedure to create 10 ship to party for single customer master.

2. how can we change Account group?

Plz send me reply

Thanks in Advance

Venkata Ramana

Add comment
10|10000 characters needed characters exceeded

  • Follow
  • Get RSS Feed

5 Answers

  • avatar image
    Former Member
    Jun 28, 2008 at 03:25 PM

    u can create new account grp & partner determination for ship to party.

    Define ship to parties and assign the same in customer master.

    hope this will help u.

    regards

    nitin

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 28, 2008 at 03:30 PM

    Hello Venkata,

    The A/c grps can be changed in transaction OBD2.

    Multiple Ship to Parties, can be maintained in a customer master: in the

    Sales view under the table Partner Functions, provided you've configured the partner determination.

    The partner determination is set up in the foll. mentu path:

    txn SPRO> Sales and Distribution>Basic Functions>Partner Determination>Set Up Partner Determination

    I hope this helps.

    Rgds,

    Raghu.

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 28, 2008 at 07:15 PM

    1.How can we get 10 shipto party at a time in customer master?

    what is the procedure to create 10 ship to party for single customer master.?

    10 different Ship to Party will have to be created individually & cannot be created under same Customer Master in SD. This Functionality is available in CRM.

    2. how can we change Account group?

    T.Code: XD07 is for Changing Account Group. But I do not think it is possible to Change Account Group, once the Customer Master is created.

    Regards,

    Rajesh Banka

    Add comment
    10|10000 characters needed characters exceeded

  • Jun 29, 2008 at 05:53 AM

    Dear Venkat Ramana

    1) Go to XD01 / VD01, select the Account Group Ship to Party and maintain the required datas and save. Like this, you have to repeat for other customers. Once you create all ship to party customers, go to XD02, select the sold to party to whom you want to assign these 10 ship to parties and execute. There select sales area data and partner function tab. There assign the customer codes and save.

    2) run XD07 to change the Account Group but if you have already transacted, then it is not possible to change the account group.

    thanks

    G. Lakshmipathi

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Jun 29, 2008 at 12:14 PM

    Hello,

    The ship-to-parties needs to be created for all the required, then assign it to the customer master --> Sales Area Data --> Partner functions tab.

    You can change the account group by transaction XD07.

    Prase