Hi Gurus,
My customer wanted to lock all the areas of PR after a PO is created by referencing to this PR. I know that we can lock the areas of PR after released, but it is a kinda different situation, because no release strategy we are using.
Thanx in advance
Hai,
1.If u want to control at PO level, make the message no 076 Materials of requisition & item & alr. ordered in full as an error message.
2.If u want to check at PR level, then use version management to track the changes done in the PR.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi Pascal,
You can use Version Management Functionality.
Setup Version Management for all the Fields in the Purchase Requisitions for which you want. It will not also users to save / change the document until proper reason is entered.
Reg,
Ashok
Rewards welcome
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
make use of the version management for pr
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hope, ur requirement is like this, no further PO should be created with reference to same PR?. If it is right, then you can control thro' messages at the PO level, make the message as an error.
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
87 | |
7 | |
6 | |
4 | |
3 | |
3 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.