Please explain d meaning of Cycle set in Maintenance plan..

Plz tell me d complete steps o fcreating Cycle set for maintenace plan

Thanks

Abhishek Vyas

Add a comment
10|10000 characters needed characters exceeded

Related questions

1 Answer

  • Best Answer
    Posted on Jun 30, 2008 at 03:50 AM

    hi

    Cycle sets are used for usage in Multiple counter plan ,if you want to perform preventive maintenance for equipment say of frequency as 200 hrs or once in 2 months.

    then you should create cycle set using IP11Z ,there you can mention the hours strategy by maintaining HRS and for months for strategy based one .(but the unit used must be same for cycle set and the measuring point created for the equipment for counter based maintenance)

    while creating the Multiple counter plan you can specify this cycle cet and create the maintenance plan,specify the link as AND or OR which means system will generate call object once the both conditions are met OR whichever comes first

    regards

    thyagarajan

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.