on 06-28-2008 9:05 AM
Dear All,
I am having one issue regarding reservation.When i reserved the material in MB21 tcode then also system issue the material & allowing reservation.
example: plant/storage location stock 20 ea
reserve 20
then also system allowed me to issue the material.
My clients want that no onw can issue the material or generate the reservation if material is already reserved.
Second can i put release strategy on reservation.means some one has create the reservation & HOD approve it.
Regards,
Dinesh Singhal
make use of the dynamic avilability check
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Dear ,
you cant make release strategy on reservation.
you can make reservation any no. of times.
system will allow for issue only if stock is more than reservation.
i think everything would be cleared,
reward if ok.
regards,
santosh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
108 | |
12 | |
11 | |
6 | |
5 | |
4 | |
3 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.