cancel
Showing results for 
Search instead for 
Did you mean: 

Progress Analysis in SAP PS

Former Member
0 Kudos

Dear Experts

I have configured the Progress analysis. I was using the Standard Measurement methods and Standard progress Version 100 and I have assigned the cost element group to Earned Value Cost element. Then I created a Project and assigned the POC and Measurement method to WBS elements and saved the Project. i have Planned cost and planned dates for the WBS Elements. Then I saved the Project, I need to calculate the earned value comparing with the Version V1. But i think, this is not happening, Can u please Guide me In configuring the Progress analysis

With Regards

S.Sangeeth Kumar

Accepted Solutions (0)

Answers (2)

Answers (2)

Former Member
0 Kudos

Dear Maria,

I dont want to do based on the statistical key figures. i need to do based on the activity and WBS Elements. My basic dates change automatically based on the activity progress.

with Regards

S.Sangeeth Kumar

MTerence
Active Contributor
0 Kudos

Hi Sangeeth,

It will be difficult to explain these things here, you need to be specific on what type of error you get, post the screenshot etc.

Also we have one blog with respect to Progress Analysis, refer below

https://blogs.sap.com/2014/12/29/progress-analysis-with-skf-in-ps/

Regards

Terence