Anyone could explain please

What is checking Rule?

What is Checking Rule PP?

What is checking Rule P1?

What is checking Rule P2?

Thanks in Advance

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

Hi,

To carry out a material availability check you need a checking group and a checking rule.

You allocate the checking group to the individual material in the material master. You specify the checking rule for each application. Together, the checking group and checking rule determine the scope of the check.

Thanks

Answers (1)

Answers (1)

dhaval_choksi3
Active Contributor
0 Kudos

Hy,

1) Checking rule Specifies whether and how the system checks availability and generates requirements for materials planning.

2) It defines, together with the checking group, the different MRP elements that make up this key figure in Flexible Planning.

Now Come to 1 point,

Along with Checking Group you can define the how system checks the material avaibility during the order processing.

For creating Chacking Control for any order type u have to define Checking grtoup along with Checking rule.

I think u can better under stand this funda(PP, P1 and P2) by handle it practically , For this pls go through below T.codes,

Define Checking Group - OVZ1

Define Checking Rule - SPRO ->Production -> Shopfloor Control ->Operations ->Avaibility Check -> Define checking Rule

Define Scope of Check - OPJJ

Define Checking Control - OPJK