on 06-27-2008 3:34 PM
Hi All,
We are doing goods issue, phase wise confirmation and goods receipt through PI sheet.
But the postings are not happening automatically. If we go and clear from transaction CO54, then only the messages PI_CONS, PI_PHST and PI_PROD are sent and then goods issue, confirmation and goods receipt postings are happening.
Please explain whether CO54 is for error processing like COGI or is an essential step.
Thanks and Regards,
Satya
Edited by: sathyanarayana naini on Jun 27, 2008 4:34 PM
Hello Sathyanarayana,
There should be a background job scheduled to send the Process messages to the corresponding destinations.
This should be a event triggered back ground job scheduled which will send the Process Messages automatically.
Here, you may refer the help at the configuration node in the Process messages --> create job for sending Process messages , from where you can find the program name for which the job needs to be scheduled.
Thanks
Mahesh
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
User | Count |
---|---|
106 | |
12 | |
11 | |
6 | |
5 | |
4 | |
4 | |
3 | |
3 | |
3 |
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.