Skip to Content
avatar image
Former Member

why does the PR has an error message after it is approved "logically deleted" why does this happen

<a href="/storage/attachments/111054-pr-logically-deleted.jpg">pr-logically-deleted.jpg</a><br>
Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

3 Answers

  • Feb 15 at 03:41 PM

    It means something terminated the workflow. Looking at your timestamps, it appears to be something within your WF or triggered by it. E.g. an update which raises an event that cancels the WF. Or an event raised in your WF.

    Add comment
    10|10000 characters needed characters exceeded

  • Feb 15 at 10:54 AM

    Hi,

    From your screenshot it is showing workflow triggered multiple times. Might be you changed mutiple time to trigger workflow multiple time. So as a rule once a workflow for same PR created, other existing workflow instance got logically deleted.

    Thanks

    Add comment
    10|10000 characters needed characters exceeded

  • avatar image
    Former Member
    Feb 20 at 12:22 AM

    Thanks Mike & Anjan

    Looks like the area cost centre was changed after the PR was created that triggered the problem.

    Add comment