on 06-26-2008 4:37 AM
I manage to perform PR (optional) and convert PR to Framework Order.
Just curious if it is possible to flow like this
PR->RFQ->Quotation->Framework Order?. If not possible, WHY?
Please advise and Thanks
Points will be rewarded handsomely
Hi,
Yes, It is possible
Regards,
You must be a registered user to add a comment. If you've already registered, sign in. Otherwise, register and sign in.
Hi,
Create PR with FO doc type and Item category B
In customization of RFQ for doc type AN Maintain B in allow Item categories
and Maintain PR doc type FO with Item category B in Link Purchase Requisitions
Now You try to create RFQ through Me41 with doc type AN
click on ref to PR and enter the PR No.
It will allow you to create RFQ
Regards,
Yes, I have configured the allowable Item category and doc type for the preceding doc type (of PR) for RFQ.
And I am able to convert. but once I have selected the PR line and click adopt+detail button.
the following error occurs
Field selection PT1A not defined
Message no. ME028
Diagnosis
The field selection required by the system is not defined in table 162. Further processing is currently not possible.
Procedure
Contact your system administrator.
Pls advise