Hi,

I have created Scheduling Agreement and maintained delivery Schedule.

No while making Good Receipt against scheduling agreement, system give message that no item exist.

I have given date in delivery schedule for e.g 27.06.2008 and I am entering good receipt on 26.06.2008. But it is not possible.

Once I change the date to 26.06.2008 in delivery schedule, then system allow to post a good receipt.

Why, Is there any setting to remove this?

Waiting for your reply.

Thanks,

Samir Bhatt

Accepted Solutions (0)

Answers (3)

Answers (3)

pankaj_singh9
Active Contributor
0 Kudos

Hi,

Definition of Scheduling Agreement: - A form of outline purchase agreement under which materials are procured on predetermined dates within a certain time period.

This means schedule lines are fixed and you can only do Goods Receipt on the prodefined schedules. If you do not want this function then better create Contracts and then PO w.r.t. Contract.

Former Member
0 Kudos

For Scheduling Agreement you should receive the delivery on the schedule date only( Delivery date)..

System will not allow you GR before delivery date..

If you want to do GR before delivery date then you should create normal PO not SA..

Former Member
0 Kudos

Friend,

We can't post GR in future date for Scheduling Agreemnt and Schedule Line scenario.