Hi all,

I need to start material cost estimate (CK11n or CK40n) for each new material created. In this project new materials are created very often and standard cost must be estimated... (as soon as possible).

It's not conceivable launch CK11N manually every time, so I need to find an alternative method.

Thanks in advance.

Accepted Solutions (1)

Accepted Solutions (1)

Former Member
0 Kudos

You can use CK40N and cost multiple products at the same time.

Thanks,

Madhav Nanduri

Answers (2)

Answers (2)

Former Member
0 Kudos

Hi Marcello

For that u can use Tcode CK40N. In this u can select a range of materials for which you want to do cost estimate.And in the same screen you can also mark and release material.

For having mark and release option in same screen you need to maintain Valuation variant and Costing variant accordingly.

hope this helps you'

Regards

Nilesh

Former Member
0 Kudos

hi u can take help of ABAPERS to creat pogramm wich will run the CK41n MASS LEVEL POGRAMM WHER IT WILL UPDATE UR material rates and costestimate.