Unable to execute Resource Load

Dear Expert,

I am having problem with Resource Load. When I tried to execute "Run Load Leveling", it appeared two messages "No operations relevant to load leveling found" and "Not possible to schedule any operations for selected resource". What am I missing? Kindly advice

Thanks and Regards,

Tandy

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Feb 12 at 08:16 AM

    Dear Tandy,

    This is expected behavior if at all you are trying to do a load leveling for Production Request or Production Order.

    Leveling can be done only for Proposals. Load leveling is possible only till load in in status Planned Production Proposal. After that load levelling is not possible.

    I hope this answers your query.

    Regards,

    Sandeep

    Add comment
    10|10000 characters needed characters exceeded

    • Hi Sandeep,

      Sorry I forgot to mention that condition in supply planning is still proposal not request/order. In this case, what should I do?

      MRP - Production proposal not yet released

      Result of Load levelling: No operations relevant to load levelling found


      Thanks and Regards,

      Tandy