Skip to Content

Unable to execute Resource Load

Feb 12 at 04:52 AM


avatar image

Dear Expert,

I am having problem with Resource Load. When I tried to execute "Run Load Leveling", it appeared two messages "No operations relevant to load leveling found" and "Not possible to schedule any operations for selected resource". What am I missing? Kindly advice

Thanks and Regards,


10 |10000 characters needed characters left characters exceeded
* Please Login or Register to Answer, Follow or Comment.

1 Answer

Sandeep Y R
Feb 12 at 08:16 AM

Dear Tandy,

This is expected behavior if at all you are trying to do a load leveling for Production Request or Production Order.

Leveling can be done only for Proposals. Load leveling is possible only till load in in status Planned Production Proposal. After that load levelling is not possible.

I hope this answers your query.



Show 1 Share
10 |10000 characters needed characters left characters exceeded

Hi Sandeep,

Sorry I forgot to mention that condition in supply planning is still proposal not request/order. In this case, what should I do?

MRP - Production proposal not yet released

Result of Load levelling: No operations relevant to load levelling found

Thanks and Regards,


mrp.png (44.3 kB)
fail-to-run.png (44.6 kB)