I am from SD side i want to know what is the use of MRP1, MRP2, MRP3 and MRP4 vies in material master

If possible send me the link

Regards

Vishal

Accepted Solutions (0)

Answers (4)

Answers (4)

Former Member
0 Kudos

thanks

Former Member
0 Kudos

Hi,

In simple words if we have to explain

MRP1 : we maintain general data,mrp procedure,lot size data

MRP2: vwe maintain procurement,scheduling,req calculation

MRP3 : We maintain forecast req,plang,avblty check

MRP4 : For BOM explosion

These data is Pulled for further processing for MRP Run.

You can refer to the link posted by one of our friend also.

Hope this will help.

Thanks,

Raja

Former Member
0 Kudos

Hi

Please go through the link

http://help.sap.com/saphelp_erp2004/helpdata/EN/ff/515c4749d811d182b80000e829fbfe/content.htm

http://help.sap.com/saphelp_erp2004/helpdata/EN/ff/515bd249d811d182b80000e829fbfe/frameset.htm

MRP1 View is used for General Planning Data _ Purchasing & Production

MRP2 View - Procuremnts, Scheduling Operations - Purcahsing & Production

MRP3 - Forecast requiremnts , Production Plannig , Sales Planning, Availbaility Cheks - Production Planning

MRP4 - Thsi view maintained only for Production Planning, Process Industry

Thanks & Regards

Kishore

Former Member
0 Kudos

Hi Vishal,

How interesting that you have put such a big issue so simply in this question. It would be difficult for anyone to explain all details as a reply to this question.

I suggest that you go to the Material Master in the MRP views and go through the individual field documentation to understand its importance. I guess the usage and necessity of each field would get highlighted as you study.

Pls dont mind the re-direction.

Cheers

Keshav

Former Member
0 Kudos

Dear Friend

I might have asked in wrong way, But i just want to know like MRP1 is used for production or which department like wise