Planning Horizon

Former Member
0 Kudos

Hi

I have set a Planning Horizon for Plant as 100 days.

Also i mantain Planning Horizon for MRP group say

MRP group "0000" - 40 days

MRP group "0001" - 30 days

MRP group "0002" - 365 days

I find that by using MRP group "0002" , the Planning Horizon of 365 is not considered (does not take into effect) during my NETPL planning run.

Can you please help !

Kris

Accepted Solutions (0)

Answers (3)

Answers (3)

Former Member
0 Kudos

This is my second shot added a little more information :

I was researching SAP help and came across this scenario. This was from KRISHNA MURTHY that you resounded to:

(have set a Planning Horizon for Plant as 100 days.

Also I maintain Planning Horizon for MRP group say

MRP group "0000" - 40 days

MRP group "0001" - 30 days

MRP group "0002" - 365 days

I find that by using MRP group "0002" , the Planning Horizon of 365 is not considered (does not take into effect) during my NETPL planning run.

Can you please help !

Kris)

My problem is : existing 100 horizon time (with MRP Controller 1002), I want to change to 356 horizon time (MRP Controller 1003).

System not reacting correctly to my MRP Controller change.

Can you explain what I am doing wrong.

If you could give me a little direction I would be very thankful.

Gailyn Wells

OXY - IT

972/448-6748

Former Member
0 Kudos

Try setting the plant planning horizon to 365 days. You then control shorter horizons with the MRP group. The net change indicator is set for changes within the planning horizon.

Regards

Laurence

Former Member
0 Kudos

This example i smy exact problem almost same scenario.

My problem is : existing 100 horizon time (with MRP Controller 1002), I want to change to 356 horizon time (MRP Controller 1003).

System not reacting correctly to my MRP Controller change.

Can you explain what I am doing wrong.

Former Member
0 Kudos

Hi.

Please letus explain your problem with an example. Outside the planning horizon are you getting any procurement proposal.

Pradeep