Hi all,
I have an material attached to the internal activity.
this internal activity is inturn attached to a network
which inturn attached to a WBS.
After the PR and PO creation of the material attached
the cost report s_alr_87013558 shows values in the
WBS element not in the network activity to the material
was attached
How to catch the cost value to network activity instead of WBS elment
Can anybody have a clue why it is happening
Thanks and Regards
pv