Costing variant-PPC3

Former Member
0 Kudos

Dear Experts

If we use costing variant -PPC3 Current cost estimate we are getting prices correctly for our valuation instead of PPC1.

But we are not able to Release cost estimates through CK24.

why we are not able to save cost estimate.

During ck24 we are getting the below message

Change selection criteria or check allowance for marking

Message no. CKCC140

Diagnosis

No data was selected for marking.

Possible causes:

There is insufficient data in the selection screen to select the required cost estimates.

The organizational measure was not carried out, or it was issued with a different costing variant to that of the cost estimates ( Marking Allowance).

All the cost estimates contain errors.

The cost estimates have already been marked or released.

For detailed information, call up the log.

Regards

Sandeep patil

Accepted Solutions (0)

Answers (1)

Answers (1)

Former Member
0 Kudos

Costing variant decides what kind of costing estimate you will create by costing run. When you run costing from CK11N , you can go to menu extras -> Information -> Costing variant to check the setting of PPC3.

You can't save: because in "update" tab "Saving allowed" hasn't been actviated.

You can't release it to material master: "control" tab, click "costing type", the setting "price update material master" is set to "no update".