Skip to Content

while planning run can we use consignment material as it is still vendor property.

while doing planning run can we consider consignment stock as it is not at our own stock? and if yes then how?

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Feb 12 at 07:47 AM

    Hi Ganesh,

    You are correct. with standard SAP we cannot. but using BAPI we can achieve it.

    Please check below SCN Thread.

    https://archive.sap.com/discussions/thread/1537497

    Hope it helps..

    Regards,

    G.V.Shivakkumar

    Add comment