I'm failed to post values of an project (cost of saled/revenue) to FI and COPA, related customizing is as following:

1. Definition of result analysis key

2. Definition of Valuation Methods for Results Analysis

3. Activation of posting to FI in Results Analysis version

4. Assignment of Allocation Structure and PA Transfer Structures to my Settlement profile

5. Check WBS settlement rule- Receiver is G/L account

6. Carry out result analysis with Tcode KKA2

7. Settlement -CJ88

However, no PA document was generated but only FI document. Please help me to check this problem, your answer is appreciated.

Regards,

Roger

Add a comment
10|10000 characters needed characters exceeded

Assigned Tags

Related questions

2 Answers

  • Posted on Jun 20, 2008 at 10:34 AM

    Hi,

    have you maintained the PSG as the settlement receiver in the settlement receiver.

    Hope it helps.

    thanks

    Add a comment
    10|10000 characters needed characters exceeded

    • Hi Donnovan,

      You do not need to maintain both settlement receivers(GL and PSG) in WBS element or MTO sales order or Service order to post to GL and COPA.

      Enter PSG as a settlement receiver and rest of the settings in RA configuration steps:

      Check your configuration steps :

      OKG1

      OKG2 -WIP and COS recognition configuration and status based configurations.

      OKG3

      OKG5 -->GL account/cost elements mapping to line ids

      OKG4 -->line ids assignment to secondary cost elements and COS/WIP assignments

      OKG8 -->secondary cost elements mapping to correct categories and GL accounts.

      In OKG8 make sure your WIPR and COSR etc categories and secondary cost elements should be mapped correctly and assigned to GL accounts(whatever P&L accounts mapped here ,do not create them as cost elements)

      Hope this helps you.

      Thanks,

      Rau

  • Posted on Jul 14, 2016 at 10:18 AM

    Hi Roger,

    As Venkat has stated, you need to only maintain PSG as settlement receiver, not GL account.

    After that follow the process that Venkat has stated.

    Additionally, check in OKG2, for your RA version, whether 'Transfer to Financial Accounting' has been checked or not.

    In order to hit FI, this must be checked.

    BR

    Abhi

    Add a comment
    10|10000 characters needed characters exceeded

Before answering

You should only submit an answer when you are proposing a solution to the poster's problem. If you want the poster to clarify the question or provide more information, please leave a comment instead, requesting additional details. When answering, please include specifics, such as step-by-step instructions, context for the solution, and links to useful resources. Also, please make sure that you answer complies with our Rules of Engagement.
You must be Logged in to submit an answer.

Up to 10 attachments (including images) can be used with a maximum of 1.0 MB each and 10.5 MB total.