Added supplement to commitment item through FMBBC not reflecting in cost element/cost center

Dear Friends

Need your quick assistance to resolve the issue

Funds added through Transaction code FMBBC - Create under supplement for the commitment item and the fund center not reflecting in the cost element and cost center Under Planned values

Values reflecting in Fund management FMAVCR01

Values not reflecting in Cost center report S_ALR_87013611 - Cost Centers: Actual/Plan/Variance

Below prerequisites are maintained

  1. OKKP: Activate Commitment Management
  2. KS02: Make sure commitments are not locked.

Followed the steeps mentioned in the below thread

https://archive.sap.com/discussions/thread/1175950

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Best Answer
    Feb 12 at 08:53 AM
    Hi, I'm not sure what your problem is. If you create budgetary document in PSM-FM, you don't have ANY impact on CO planning. This is perfectly normal. There could be an opposite connection, i.e. values introduced in CO planning can be 'converted' to budgetary documents via special program, but not vice versa. Regards, Eli