Orders Scheduling in SAP PM Plan

I have a PM Plan for a 20 Control Valves. All the PM Orders are generated on Single Day & Time. Since the duration for each Order is 8 hours, all the 20 Orders to be closed on the same day which practically not possible.

Is there any way to have this PM Plan for 20 days and all the internal Orders are scheduled accordingly, I mean one day each Job.

Add comment
10|10000 characters needed characters exceeded

  • Get RSS Feed

1 Answer

  • Feb 13 at 05:04 AM

    Hi,

    Is the plan for every 20 days for all 20 Control valves ? Like, if the Plan 1 called Todaye 13.02.2018, so the next order to be called on 04.03.2018.

    Create a single cycle plan with 20 day cycle and set the cycle start, so the next order will be scheduled accrodingly.

    Regards

    Terence